Engineering Logistics
JB Rawcliffe & Sons Ltd has just completed the handling and transportation of a 63,000kg RCR Energy boiler from Tilbury Docks to Nestlé’s Project Dove state of the art coffee factory in Tutbury.
12 months in the planning, JB Rawcliffe & Sons Ltd were involved from the beginning when we were contacted and contracted to complete a route survey for the boiler at 15179mm long x 5328mm wide x 4637mm high from the UK port of entry to the delivery site for the boiler which was shipped from New Zealand. JB Rawcliffe & Sons Ltd liaised with the Highway Agency and police to obtain the necessary road permits for the movement.
In conjunction with RCR Energy JB Rawcliffe & Sons Ltd were able to assist in the engineering, design and manufacture the end suspension bookends which allowed the boiler to be supported and suspended from bolsters located on Nicolas MDED modular axles at each end.
JB Rawcliffe & Sons Ltd accepted the boiler at Tilbury Dock were we fitted our bookends to the boiler and removed the base shipping frame for the successful delivered to site.
Hot Trommel
JB Rawcliffe & Sons Ltd has successfully completed a two part project for the removal of a fire damaged trommel and installation of a new trommel.
The trommel 14.5m x 3.95m x 4.2m 35,000kg was located 5.4m above the ground with limited headroom and surrounded by associated components making it a very tricky operation. Due to its ability to operate in confined spaces and lift capacity at high level lifting JB Rawcliffe & Sons Ltd utilised the 300Ton capacity lift system to lift the trommel from its support legs which were removed and lowered the trommel down to a super low steerable semi low loader for the removal from site.
The second part of the project was the installation of a new trommel which was delivered in from Europe. Due to the limited access on site JB Rawcliffe & Sons Ltd supplied a steerable semi low loader for the trommel to be transhipped onto. Again the 300Ton capacity lift system was used and the trommel lifted and placed onto its support legs. Both parts of the project were completed within schedule, budget and without incident.