JB RAWCLIFFE & SONS LTD
Heavy & Abnormal Transport Specialists
 

Installation Documentary

Removal Of A 65,000kg Transformer At Ironbridge Power Station.

1. Ground preparations for 20m journey across grass.

2. Transformer to be removed.

3. Transformer making its way towards road.

4. Progression is steady and sure.

5. Arriving at trailer.

6. 90° rotation for road transport.

7. Ready for departure.
Photos Courtesy Of Mr. D Finn

Installation of a 70,000kg transformer at Cottam Power Station.

1. Arrival of transformer

2. Transformer positioned & runway constructed

3. Transformer rotated for endways travel

4. Transformer is steadily skated towards final position

5. Skating complete & prepared for jacking down

6. Operation complete with transformer placed in final position


Sitemap
eXTReMe Tracker
Website Builder - Freestart Premier Websites